Allow ECG to deliver its mandate without the usual political interference – IES tells gov’t

Spread the love

Concerns have been raised by the Institute for Energy Security (IES) about apparent contradictions in the Electricity Company of Ghana’s (ECG) public remarks on the most recent national blackouts.

The IES is skeptical of the government’s and ECG’s statements that there is no load shedding, noting technical problems such the repair of overloaded electricity transformers.

The IES questioned ECG’s claim of a “stable national power supply,” calling it deceptive, in a statement dated April 1 and signed by Nana Amoasi VII, its executive director.

The IES emphasized that a reliable national grid is still a goal, drawing attention to the disparity between the claims made by ECG and the current situation of Ghana’s power subsector.

Since the beginning of the year, ECG has continuously received less than 85% of the needed electricity from GRIDCo, raising doubts about the viability of a constant power supply. The IES called for a more open and honest communication strategy from the utility company.

“In any case, how can we have a stable national power supply when since the start of the year, the ECG barely receives from GRIDCo 85% of power required to fully meet the demand of its customers. Again, one wonders the capacity of the ECG to confidently suggest that Ghana has a stable national grid” the statement captured.

Additionally, the IES recommended that GRIDCo take a more proactive approach to resolving grid stability and power supply stability-related concerns as the system operator.

“The Ghana Grid Company Limited (GRIDCo) must break its silence on happenings in the power sector and be willing to indicate to the Electricity Company of Ghana (ECG) the quantum of power that could be made available to the ECG within a set time frame. Such an information is vital for the ECG to plan its load response with a timetable”.

They also urged the Minister of Energy and government to stop political interference “The Minister of Energy, and by extension, the government must allow the ECG to freely deliver its mandate without the usual political interference. The best intervention Ghanaians can expect from government at this critical moment is to cause the ECG and GRIDCo to cooperate so a load-shedding timetable can be issued as expected by Ghanaians”.

Read the full statement below:

“THE INCONSISTENCIES IN ELECTRICITY COMPANY OF GHANA’S (ECGs) EXECUSES MAY DENT ITS REPUTATION” IES’ Observations

The attention of the Institute for Energy Security (IES) has been drawn to yet another statement from the Electricity Company of Ghana (ECG), which states that “The Electricity Company of Ghana wishes to inform our cherished customers and the general public that we have a stable national power supply (stable national grid).”

The IES is scandalised by this misleading statement, and the inconsistencies in ECG’s public releases relative to the recent power outages being recorded across the country.

In the recent statement, the ECG sought to equate “stable national power supply” to “stable national grid,” both of which are non-existent in our present power sub-sector.

The IES is appalled by the extent to which the ECG is permitting the powers that be to frustrate its eligible business and to embarrass itself in the eye of the public. These public relation (PR) gimmicks by the ECG are unwarranted, disgusting, and diversionary; capable of denting the reputation and credibility of the institution.

In any case, how can we have a stable national power supply when since the start of the year, the ECG barely receives from GRIDCo 85% of power required to fully meet the demand of its customers. Again, one wonders the capacity of the ECG to confidently suggest that Ghana has a stable national grid.

Where the power sector finds itself today, the best utility to speak to issues of power supply stability and grid stability Is the system operator the Ghana Grid Company Limited (GRIDCo). Unfortunately, GRIDCo has gone mute, an attitude uncharacteristic of the entity.

IES’ Demands

1. The Ghana Grid Company Limited (GRIDCo) must break its silence on happenings in the power sector and be willing to indicate to the Electricity Company of Ghana (ECG) the quantum of power that could be made available to the ECG within a set time frame. Such an information is vital for the ECG to plan its load response with a timetable.

2. The ECG must concern itself with its load management based on the quantum of power made available by GRIDCo, as well as its effective mobilisation of revenue; necessary to prove full cost recovery.

3. The Public Utility and Regulatory Commission (PURC) must look beyond the ECG to audit the upstream segment of the power sub-sector, particularly the GRIDCo, and export sales by the Volta River Authority (VRA).

4. The Minister of Energy, and by extension, the government must allow the ECG to freely deliver its mandate without the usual political interference. The best intervention Ghanaians can expect from government at this critical moment is to cause the ECG and GRIDCo to cooperate so a load-shedding timetable can be issued as expected by Ghanaians.

Thank you.

SIGNED
NANA AMOASI VII
EXECUTIVE DIRECTOR, IES

Source: Ghanatodayonline.com

About admin

Check Also

2024 Election: Fanteakwa North NDC PC sues EC

Spread the love In an attempt to stop the alleged re-declaration of the parliamentary election …

Leave a Reply

Your email address will not be published. Required fields are marked *